Saudi government tenders run through Etimad, the Ministry of Finance’s procurement portal. A new procurement law applies to them from 2 January 2027. Tenders issued before then stay under the old law. A credible submission starts with knowing which rules your tender follows.
Short answer: Etimad is the Saudi government’s unified e-procurement portal, and you need to be registered on it to bid. Tenders issued before 2 January 2027 stay under the 2019 law. Later tenders follow the new law, Royal Decree M/76. It sets a 1% to 2% bid guarantee, a 5% final guarantee, 90 working days of offer validity and technical evaluation before price. Its Implementing Regulation and Preference Regulation are still drafts, so read each tender’s documents.
This guide is built from official sources, mainly the law text on the Umm Al-Qura legal portal, and from law firm summaries. It does not draw on the author’s own Etimad bids. Each rule links to its source with the date it was checked. This is not legal advice.
What Etimad Is
Etimad is the portal through which Saudi government entities buy, and through which contractors bid. The Ministry of Finance describes it as a “unified digital services platform” for government entities and private sector contractors (Ministry of Finance, checked 30 October 2026).
The General Authority for Statistics (GASTAT) says the platform lets the private sector “receive invitations, purchase RFPs and apply electronically”. An RFP is a request for proposals, the tender documents you buy and respond to (GASTAT, checked 30 October 2026).
You can browse current tenders before you register. Etimad publishes a public tender list for visitors at tenders.etimad.sa (checked 30 October 2026).
The new law, which applies from 2 January 2027, confirms the portal’s role. Article 1 defines it as a unified e-portal for government procurement under the Ministry of Finance’s supervision. Article 16 requires tenders and government purchases to run through it, unless technical or national-security reasons prevent that (Royal Decree M/76, UQN, checked 30 October 2026).
From 2 January 2027, Article 4 of the new law gives qualified bidders equal opportunities and equal treatment.
To bid, you need to be registered on the portal. Take the current document requirements from Etimad itself rather than from third-party lists, which can be out of date. If you are an EPC contractor targeting Saudi public projects, registration is the first step.
Which Rules Apply to Your Tender
The tender’s issue date decides which law governs it. Royal Decree M/76 was published in Umm Al-Qura on 4 September 2026. Article 101 says it applies 120 days after publication. Baker McKenzie puts that date at 2 January 2027 (Baker McKenzie, checked 30 October 2026).
Article 100 states that the new law replaces the 2019 Government Tenders and Procurement Law, Royal Decree M/128. Item Third of Royal Decree M/76 keeps tenders issued while the 2019 law was in force under that law (UQN, checked 30 October 2026).
Transition at a glance (checked 30 October 2026)
- Tender issued before 2 January 2027: the 2019 law (Royal Decree M/128) governs it, under Item Third of Royal Decree M/76.
- Tender issued from 2 January 2027: the new law (Royal Decree M/76) governs it, under Article 101 and Baker McKenzie’s date.
- New Implementing Regulation and Preference Regulation: due within 120 days under Articles 98(2) and 99. Both were still drafts when checked.
This guide does not summarise the 2019 law article by article. For tenders under it, the tender documents and the 2019 law text govern. When the Ministry of Finance announced that law in July 2019, it said local small and medium enterprises (SMEs) were exempt from the initial guarantee (Ministry of Finance, 16 July 2019, checked 30 October 2026).
The draft Regulations will fill in much of the detail. Their contents are not covered here, because drafts can change before they are issued.
One more caution: the UQN page for the new law is labelled a trial version and was last modified on 7 October 2026. Check the official text again before you rely on an article.
What the New Law Sets for Bidders
The points below apply to tenders under Royal Decree M/76, from 2 January 2027. All article references are to the law text on UQN (Royal Decree M/76, checked 30 October 2026).
Bid and final guarantees
Under the new law (from 2 January 2027), Article 41(1) sets the initial guarantee, often called the bid bond, at 1% to 2% of the offer value. An offer without it is not accepted. Arrange the guarantee early, because a missing one ends the bid.
Article 42(1) lists exemptions. They include contracts with local SMEs, direct purchase and urgent cases.
The exemption has a condition. Under Article 42(2), an exempt bidder who would otherwise have forfeited the guarantee pays a 2% fine. The alternative is referral to the Article 87 committee, which can ban a bidder for up to one year.
If you win a tender under the new law, Article 59(1) requires a final guarantee of 5% of the contract value. It is due within 15 working days of the award notice, and that period can be extended once.
Technical and financial files
Under the new law (from 2 January 2027), Articles 43(2) and 44(2) put the technical offer ahead of the financial one. Where a tender uses two files, a technical offer that fails means the financial offer is returned unopened.
Treat the technical offer as a complete document in its own right, with every requested item answered.
Deadlines and offer validity
Under the new law (from 2 January 2027), Article 36(2) says late offers are not accepted. Article 39(1) keeps offers valid for 90 working days from the opening of offers.
Ninety working days is a long time for equipment prices and supplier quotes. Check that your own suppliers’ quotes stay valid for that period, or price the risk in.
What the law does not fix
The law does not set a price for tender documents. Article 21(3) leaves the criteria for that price to the Implementing Regulation. Article 49(1) deals with refunds when a tender is cancelled. Check the document price in each tender rather than assuming a standard fee.
Local Content and the Regional Headquarters Rule
Local content can change how your offer is scored or priced. From 2 January 2027, Article 9 of the new law gives priority to local SMEs, local content and listed companies, as the Preference Regulation sets out. The new Preference Regulation is still a draft (UQN, checked 30 October 2026).
Under the new law, from 2 January 2027, Article 3(2) adds a limit for foreign firms. Persons licensed outside the Kingdom may be used only under conditions the Regulation sets, with local licensed suppliers considered first.
Clyde & Co describes how the current Preference Regulation works. It is Council of Ministers Resolution 245 of 2019. Foreign products not on the Mandatory List of the Local Content and Government Procurement Authority (LCGPA) can be evaluated as if “priced 10% higher than their stated bid price”. Clyde & Co adds that some tenders score a bidder’s local content (Clyde & Co, checked 30 October 2026).
Baker McKenzie notes that the new law strengthens LCGPA’s role. Expect local content to matter at least as much under the new regime.
Regional headquarters
For Aramco’s own supplier registration, which runs separately from Etimad, see Saudi Aramco vendor registration and iktva. Foreign firms also face a regional headquarters rule. Gulf News reported in February 2026 that, since 2024, contracting with foreign firms whose regional headquarters is outside the Kingdom has been restricted (Gulf News, 21 February 2026, checked 30 October 2026).
According to that report, an exception process runs through Etimad. A foreign bid can be accepted if it is the only technically compliant bid. It can also be accepted if it is the best bid and “priced at least 25% lower than the next competitor”. Projects of SAR 1 million or less are exempt.
These points come from a news report, not from an official text checked for this guide. Confirm the current rule with LCGPA before you bid.
A Submission Checklist Mapped to the Law
Use this checklist for tenders under the new law. For tenders issued before 2 January 2027, the article references do not apply. Take guarantee, validity and evaluation rules from the tender documents, and still submit a complete technical file through Etimad before the deadline. Article references are to Royal Decree M/76 on UQN (checked 30 October 2026).
| Check | What to confirm | Source |
|---|---|---|
| Governing law | The tender’s issue date: before or from 2 January 2027 | Royal Decree M/76, Item Third; Art. 101 |
| Portal | Your company is registered, and you submit through Etimad | Art. 16 |
| Bid guarantee | A guarantee of 1% to 2% of the offer value is attached | Art. 41(1) |
| SME exemption | Whether you qualify, and your exposure to the 2% fine or Art. 87 ban | Art. 42(1), 42(2) |
| Technical file | Complete on its own; it is examined before price | Art. 43(2), 44(2) |
| Deadline | Submitted before closing; late offers are not accepted | Art. 36(2) |
| Offer validity | Your prices and supplier quotes hold for 90 working days | Art. 39(1) |
| Final guarantee | 5% of contract value ready within 15 working days of award | Art. 59(1) |
| Tender documents | The price stated in this tender, and refund terms on cancellation | Art. 21(3), 49(1) |
| Local content | Mandatory List items and any local content scoring | Art. 9; Clyde & Co |
| Foreign licence | Conditions for persons licensed outside the Kingdom | Art. 3(2) |
| Regional HQ | Whether the restriction or an exception applies to you | Gulf News; confirm with LCGPA |
Give one person ownership of the guarantee dates. The bid guarantee, the 90-day validity and the 15-day final guarantee window all run on separate clocks.
How Your Public Profile Supports a Bid
The law does not say evaluators look at your website. Still, your technical offer makes claims about capacity, projects and certifications. Anyone reviewing it can look you up online and compare.
What usually weakens a profile is a gap between the offer and the public record. Check whether your site shows the same scope, project references and certificates as your technical file. Dates matter: an expired certificate online raises questions.
For Saudi buyers, also check whether your key pages exist in Arabic. A named contact with a direct phone number helps an evaluator who needs to clarify a point.
The wider picture of registration, qualification and bidding is covered in the GCC supplier pre-qualification guide. If your site does not yet match your tender documents, see website design for pre-qualification checks.
Frequently Asked Questions
Do I need to register on Etimad to bid for Saudi government tenders?
Yes. Bidding on government tenders requires registration on the portal. From 2 January 2027, Article 16 of the new law requires tenders to run through it, with narrow exceptions. Take the current registration requirements from Etimad directly.
Does the new law apply to a tender issued in December 2026?
No. Item Third of Royal Decree M/76 keeps such tenders under the 2019 law. The new law applies from 2 January 2027.
Are local SMEs exempt from the bid guarantee under the new law?
Article 42(1) lists contracts with local SMEs among the exemptions. Under Article 42(2), an exempt bidder who would have forfeited the guarantee pays a 2% fine or faces the Article 87 committee. That committee can impose a ban of up to one year.
Can a foreign company win a tender without a regional headquarters in Saudi Arabia?
Gulf News reported that a foreign bid can be accepted if it is the only compliant bid, or the best and priced at least 25% lower than the next. Projects of SAR 1 million or less are exempt. Confirm with LCGPA.
Before You Submit
Start with the issue date, because it decides which law applies. Under the new law, plan the bid guarantee, a complete technical file and 90 working days of validity. Check local content and the regional headquarters position before you price.
Programme rules change; check the current requirements with Etimad, the UQN law text and LCGPA. Checked: 30 October 2026.
Your public profile is part of what a reviewer can check. To see how your site reads next to a technical offer, request a free website audit.
About the Author
Danil Shtankov is the founder of Wattpixel. He spent five years in power generation business development. Read more about Wattpixel or follow Wattpixel on LinkedIn.
Sources
- Royal Decree M/76, Government Tenders and Procurement Law, Umm Al-Qura legal portal (UQN) (published 4 September 2026; page labelled trial version, modified 7 October 2026; checked 30 October 2026)
- Baker McKenzie, “Saudi Arabia: key changes under new government procurement law” (21 October 2026; checked 30 October 2026)
- Ministry of Finance, “Ministry of Finance launches Etimad, the digital services platform” (checked 30 October 2026)
- Ministry of Finance, Minister of Finance on approval of the Government Tendering and Procurement Law (16 July 2019; checked 30 October 2026)
- General Authority for Statistics (GASTAT), “Tenders and procurement” (checked 30 October 2026)
- Etimad, public tender list for visitors: tenders.etimad.sa/Tender/AllTendersForVisitor (checked 30 October 2026)
- Clyde & Co, “Local content in Saudi” (September 2026; checked 30 October 2026)
- Gulf News, “New rule: Saudi Arabia reverses restriction, allows foreign companies in government projects” (21 February 2026; checked 30 October 2026)